Regulatory Matters (Tables)
6 Months Ended
Jun. 30, 2025
Public Utilities General Disclosures [Line Items]  
Summary of Significant Virginia Power Electric Transmission Projects Applied

Description and Location of Project

 

Application
Date

 

Approval
Date

 

Type of
Line

 

Miles of
Lines

 

Cost Estimate
(millions)
(1)

 

Construct new Aspen and Golden substations, transmission lines and related
    projects in Loudoun County, Virginia

 

March 2024

 

February 2025(2)

 

500-
230 kV

 

10

 

$

705

 

Construct new Apollo-Twin Creek transmission lines, new substations and related
    projects in Loudoun County, Virginia

 

March 2024

 

February 2025(2)

 

230 kV

 

2

 

 

285

 

Rebuild and construct new Fentress-Yadkin transmission lines and related projects
    in the City of Chesapeake, Virginia

 

June 2024

 

February 2025

 

500 kV

 

14

 

 

205

 

Partial rebuild, reconductor and construct new Network Takeoff transmission lines
    and related projects in the Counties of Fairfax and Loudoun, Virginia

 

July 2024

 

March 2025

 

230 kV

 

6

 

 

170

 

Rebuild Aquia Harbour-Possum Point transmission lines and related projects in the
    Counties of Stafford and Prince William and the City of Fredericksburg, Virginia

 

August 2024

 

March 2025

 

500-
230 kV

 

32

 

 

210

 

Partial rebuild, reconductor and construct new New Post transmission lines and
    related projects in the Counties of Caroline and Spotsylvania, Virginia

 

August 2024

 

May 2025

 

230 kV

 

38

 

 

120

 

Construct new Centreport transmission line, substation and related projects in
    Stafford County, Virginia

 

September 2024

 

June 2025

 

230 kV

 

3

 

 

55

 

Partial rebuild and construct new Meadowville transmission lines, substations and
   related projects in Chesterfield County, Virginia

 

October 2024

 

June 2025

 

230 kV

 

11

 

 

190

 

Construct new Technology Boulevard transmission lines, substation and related
    projects in Henrico County, Virginia

 

March 2025

 

Pending

 

230 kV

 

5

 

 

60

 

Construct new Hornbaker transmission lines, switching station and related projects
    in Prince William County, Virginia

 

March 2025

 

Pending

 

230 kV

 

5

 

 

95

 

Construct new Golden-Mars transmission lines and related projects in Loudoun
    County, Virginia

 

March 2025

 

Pending

 

500-
230 kV

 

11

 

 

525

 

Construct new Duval-Midlothian transmission lines, substation and related
    projects in Chesterfield County, Virginia

 

April 2025

 

Pending

 

230 kV

 

7

 

 

125

 

Rebuild Chickahominy-Elmont transmission line, new future transmission line and
   related projects in the Counties of Charles City, Henrico and Hanover, Virginia

 

May 2025

 

Pending

 

500-
230 kV

 

28

 

 

190

 

Rebuild Septa-Yadkin transmission line, partial rebuild of Suffolk-Thrasher
   transmission line and related projects in Isle of Wight County and the Cities of
   Chesapeake and Suffolk, Virginia

 

June 2025

 

Pending

 

500-
230 kV

 

33

 

 

250

 

 

(1)
Represents the cost estimate included in the application except as updated in the approval if applicable. In addition, Virginia Power had various other transmission projects approved during 2025 or applied for and currently pending approval with aggregate cost estimates of approximately $32 million and $33 million, respectively.
(2)
The final order of the Virginia Commission has been appealed to the Supreme Court of Virginia. This matter is pending.
Virginia Electric and Power Company  
Public Utilities General Disclosures [Line Items]  
Significant Riders Associated With Virginia Power Projects

Rider Name

 

Application
Date

 

Approval
Date

 

Rate Year
Beginning

 

Total Revenue
Requirement
(millions)
(1)

 

 

Increase (Decrease)
from Previous
(millions)

 

Rider CCR(2)

 

April 2025

 

Pending

 

January 2026

 

$

166

 

 

$

63

 

Rider CE(3)

 

October 2024

 

April 2025

 

May 2025

 

 

182

 

 

 

49

 

Rider DIST(4)

 

August 2024

 

May 2025

 

June 2025

 

 

267

 

 

N/A

 

Rider GEN(5)

 

June 2024

 

February 2025

 

April 2025

 

 

438

 

 

N/A

 

Rider GEN

 

June 2024

 

February 2025

 

April 2026

 

 

311

 

 

 

(127

)

Rider SNA(6)

 

October 2024

 

July 2025

 

September 2025

 

 

207

 

 

 

138

 

Rider T1(7)

 

May 2025

 

Pending

 

September 2025

 

 

1,343

 

 

 

173

 

 

(1)
In addition, Virginia Power has riders associated with other projects with a total annual revenue requirement of $42 million and a pending application associated with the Chesterfield Energy Reliability Center described above, which if approved would result in a net annual revenue requirement increase of $36 million.
(2)
In connection with this application, Virginia Power also requests to extend existing rates for Rider CCR by one month through December 2025.
(3)
Associated with two solar generation projects, two small-scale solar projects and 19 purchased power agreements in addition to previously approved Rider CE projects.
(4)
Rider DIST includes $100 million in total revenue requirement for certain previously approved electric distribution grid transformation projects and $167 million for previously approved phases and proposed phase eight of certain new underground distribution facilities. Rider DIST also results in the consolidation of, and ceases the separate collection of rates under, Riders GT and U effective June 1, 2025.
(5)
Rider GEN includes $348 million in total revenue requirement related to the consolidation of Riders BW, GV and four other riders associated with generation facilities, ceasing the separate collection of rates under these riders effective April 1, 2025 and the extension of existing rates for Rider BW through March 2025. In addition, Virginia Power also received approval to recover costs associated with the Virginia LNG Storage Facility through Rider GEN described in Note 13 to the Consolidated Financial Statements in the Companies’ Annual Report on Form 10-K for the year ended December 31, 2024.
(6)
The Virginia Commission also approved Virginia Power’s request for cost recovery of approximately $1.7 billion through Rider SNA for the second phase of the nuclear life extension program which includes investments for calendar years 2025 through 2027.
(7)
Consists of $561 million for the transmission component of Virginia Power’s base rates and $782 million for Rider T1.