Schedule of Lease Costs
The components of lease expense were as follows (in millions):
Three Months EndedSix Months Ended
Lease CostClassificationJune 29, 2025June 30, 2024June 29, 2025June 30, 2024
Finance lease cost:
Amortization of right-of-use assetsCost of goods sold$0.1 $— $0.3 $— 
Amortization of right-of-use assetsSelling, general and administrative expenses8.6 7.1 16.7 13.3 
Interest on lease liabilitiesInterest and other non-operating expenses, net2.4 1.6 4.6 3.0 
Operating lease costCost of goods sold2.1 2.1 4.1 4.1 
Operating lease costSelling, general and administrative expenses27.0 24.1 52.1 48.4 
Short-term lease costCost of goods sold0.2 — 0.3 — 
Short-term lease costSelling, general and administrative expenses0.7 1.2 2.0 2.1 
Variable lease costSelling, general and administrative expenses0.3 0.7 0.8 1.6 
Sublease incomeSelling, general and administrative expenses(0.3)(0.3)(0.5)(0.5)
Total lease cost$41.1 $36.5 $80.4 $72.0 

Supplemental cash flow information related to leases was as follows (in millions):
Three Months EndedSix Months Ended
Other InformationJune 29, 2025June 30, 2024June 29, 2025June 30, 2024
Cash paid for amounts included in the measurements of lease liabilities:
Operating cash flows from finance leases$2.4 $1.6 $4.6 $3.0 
Operating cash flows from operating leases$29.4 $26.2 $58.2 $53.6 
Financing cash flows from finance leases$8.1 $6.5 $15.8 $12.3 
Right-of-use assets obtained in exchange for new lease liabilities:
Finance leases$14.6 $16.5 $26.1 $32.3 
Operating leases$28.8 $37.5 $44.1 $50.1 
The weighted-average lease terms and discount rates were as follows:
Lease Term and Discount RateJune 29, 2025June 30, 2024
Weighted-average remaining lease term:
Finance leases4.5 years4.6 years
Operating leases5.9 years6.2 years
Weighted-average discount rate:
Finance leases6.7 %6.4 %
Operating leases5.5 %5.3 %
Schedule of Future Lease Payments for Operating Leases
The aggregate future lease payments for operating and finance leases as of June 29, 2025 were as follows (in millions):
Maturity of Lease LiabilitiesOperating LeasesFinance Leases
Fiscal year:
2025 (remainder)$48.0 $20.6 
2026104.2 38.9 
202790.0 35.0 
202873.7 31.1 
202960.2 22.9 
203042.2 11.4 
Thereafter94.7 1.7 
Total lease payments513.0 161.6 
Less: interest81.7 21.3 
Present value of lease liabilities$431.3 $140.3 
Schedule of Future Lease Payments for Finance Leases
The aggregate future lease payments for operating and finance leases as of June 29, 2025 were as follows (in millions):
Maturity of Lease LiabilitiesOperating LeasesFinance Leases
Fiscal year:
2025 (remainder)$48.0 $20.6 
2026104.2 38.9 
202790.0 35.0 
202873.7 31.1 
202960.2 22.9 
203042.2 11.4 
Thereafter94.7 1.7 
Total lease payments513.0 161.6 
Less: interest81.7 21.3 