Exhibit 4.27
Notice of Approval for Change in Repayment Terms
Japan Finance Corporation – Small and
Medium Enterprise Division, Senju Branch
Date: December 20, 2024
To: Tokyo Lifestyle Co., Ltd.
(130-0022 Tokyo-to, Sumida-ku, Koutoubashi 2-5-9)
Based on your request submitted in the attached “Request for Change in Repayment Terms”, we hereby inform you that we approve the temporary change in the repayment conditions for the loan detailed below, in accordance with the attached “Repayment Schedule Table”.
Loan Subject to Modification of Repayment Terms
● | Loan Date: June 22, 2018 |
● | Loan No.: 225110 |
● | Transaction Reference No.: cn60103 20241220 094343 |
Repayment Schedule Table
(Loan No.: 225110)
To: Tokyo Lifestyle Co., Ltd.
Loan Date: June 22, 2018
(Date of Change): December 20, 2024
Loan Amount: ¥200,000,000
Use of Funds: Equipment
Type of Claim: Industrial Facility
New Maturity Date: April 30, 2025
Installments: 1
Repayment Frequency: Monthly
Payment Date | Principal | Interest | Total Payment | Remaining Balance | Days | Interest Rate | ||||||||||||||
Dec. 19, 2024 | ¥ | 0 | ¥ | 314,293 | ¥ | 314,293 | 3.20 | % | ||||||||||||
Dec. 31, 2024 | ¥ | 0 | ¥ | 198,500 | ¥ | 198,500 | ¥ | 188,679,200 | 12 | 3.20 | % | |||||||||
Jan. 31, 2025 | ¥ | 0 | ¥ | 512,793 | ¥ | 512,793 | ¥ | 188,679,200 | 31 | 3.20 | % | |||||||||
Feb. 28, 2025 | ¥ | 0 | ¥ | 463,168 | ¥ | 463,168 | ¥ | 188,679,200 | 28 | 3.20 | % | |||||||||
Mar. 31, 2025 | ¥ | 0 | ¥ | 512,793 | ¥ | 512,793 | ¥ | 188,679,200 | 31 | 3.20 | % | |||||||||
Apr. 30, 2025 | ¥ | 188,679,200 | ¥ | 496,252 | ¥ | 189,175,452 | - | 30 | 3.20 | % |
Bank for Automatic Debit:
Sumitomo Mitsui Banking Corporation
(SMBC), Kameido Branch
Account Type: Ordinary
Important Notes
1. | If “Separate Notification” is written in the first row of the table above, a separate payment notice will be sent from the Corporation. Please follow the instructions contained therein. |
2. | After the full disbursement of the loan amount, you are required to make payments of the principal and
accrued interest as per the schedule. If payments are delayed for any reason, a late penalty interest of 8.9% per annum will apply
to the unpaid principal. In such cases, please include the additional amount when making the payment. Note: If the scheduled payment date falls on a holiday, payment made on the next business day will not incur a penalty. |
Example Calculation:
o | Scheduled Date: 10th |
o | Actual Payment Date: 25th |
o | Principal: ¥500,000 |
o | Interest: ¥27,125 |
o | Total Payment Due: ¥527,125 |
o | Late Penalty: ¥500,000 × 8.9% × 15 / 365 = ¥1,828 |
o | Total Amount to Pay: ¥528,953 (Note: Use 365 days even in leap years.) |
3. | If there was any underpayment or overpayment in your previous payment, the amounts in this table may not apply. We will contact you in such cases. |
4. | Every effort has been made to ensure the accuracy of the calculations above, but if you have any questions or concerns, please contact us. |