Commitments

The following table summarizes REE’s contractual obligations and other commitments for cash expenditures as of December 31, 2024, and the years in which these obligations are due. Certain obligations are reflected in the balance sheet, while other are disclosed as future obligations. This table is not meant to represent a forecast of the Company’s total cash expenditures for any of the periods presented.

Purchase commitments
2025$26,200 
Total$26,200 

Open purchase orders that are cancellable are not considered unconditional purchase obligations for financial reporting purposes and are not included in the table above. Such purchase orders often represent authorizations to purchase rather than binding agreements.

Guarantee

A long-term guarantee was issued by a bank in the amount of approximately $2,510 was recorded within long-term restricted cash to secure the Company’s office and manufacturing locations.

Royalty bearing grants

Until 2018, the Company’s research and development efforts had been partially financed through grants from the Israeli Innovation Authority (“IIA”) for the technology related to the Softwheel legacy activity. Under the research and development agreements with the IIA, if the Company does not generate revenues from products developed with funds provided by the IIA, the Company is not obligated to pay royalties or repay the grants. As of December 31, 2024, the Company’s remaining contingent obligation with respect to royalty-bearing participation received or accrued, net of royalties paid or accrued, were $741. Since the Company does not anticipate generating revenues from products developed with funds provided by the IIA, it does not expect to make any repayments to the IIA.

In 2018, the Company signed a research and development agreement with the Israel-United States Binational Industrial Research and Development Foundation (“BIRD”). Under this agreement, if the Company does not generate revenues from products developed with funds provided by the BIRD, the Company is not obligated to pay royalties or repay the grants. As of December 31, 2024, the BIRD contingent liability with respect to royalty-bearing participation received or accrued, net of royalties paid or accrued, totaled $433. Since the Company does not anticipate to generating revenues from products developed with funds provided by the BIRD, it does not expect to make any repayments to the BIRD.
NOTE 9. COMMITMENTS AND CONTINGENT LIABILITIES (cont.)

Legal proceedings

On December 16, 2022, a lawsuit was filed to the court in Texas, Austin Division, against REE and its US subsidiaries (in this section, the “Group”), by OSR Group alleging that the Group stole OSR Group’s trade secrets. The OSR Group requested the court to grant them the following: (a) a request for an injunction pertaining to the use of such trade secrets; (b) affirmative action to protect the OSR Group’s alleged trade secrets; (c) the establishment of a constructive trust to transfer all the relevant Group’s legal title and intellectual property to the OSR Group; (d) an award to the OSR Group of monetary damages in an amount of no less than USD 2.6 billion together with exemplary damages in an amount of no less than USD 5.2 billion, such amounts to be determined in the trial, plus interest; (e) an award to the OSR Group for all of its expenses relating to the action; (f) an award to the OSR Group of pre-judgment interest on all damages; and (g) an award of other relief as the court deem fit. On January 4, 2024, the Magistrate Judge entered a Report and Recommendation (“Report”), recommending dismissal of the lawsuit based on forum non conveniens, such that OSR could pursue its claims in an Israeli forum rather than in the United States, assuming that OSR chooses to do so after dismissal. On August 26, 2024, the District Judge adopted the Report, granting REE’s motion to dismiss for forum non conveniens and ordering the clerk of the court to close the case. On September 26, 2024, OSR filed a Notice of Appeal to the United States Court of Appeals for the Fifth Circuit, appealing the District Judge’s adoption of the Report and dismissal of the case for forum non conveniens. The appeal is currently pending and there is no definitive timetable for a final ruling. Given the uncertainty of litigation and the preliminary stage of the lawsuit, the Company cannot estimate the reasonably possible loss or range of loss that may result from this lawsuit. As of December 31, 2024 and December 31, 2023 the Company did not record a loss contingency.
Notwithstanding the foregoing, from time to time, REE may become involved in actions, claims, suits, and other legal proceedings, such as requests to disclose information before initiating derivative cases, arising in the ordinary course of the Company's business, including but not limited to claims related to employment, intellectual property and shareholder matters.