Vogtle Units No. 3 and No. 4 Construction Project - Narrative (Details) - Vogtle Units No. 3 & No. 4
$ in Thousands
3 Months Ended 12 Months Ended
Mar. 31, 2025
USD ($)
unit
MW
Dec. 31, 2024
USD ($)
Dec. 31, 2023
USD ($)
Public Utility Property Plant and Equipment      
Ownership interest (as a percent) 30.00%    
Georgia Power      
Public Utility Property Plant and Equipment      
Nuclear production tax credit $ 24,424 $ 72,600 $ 21,700
EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.      
Public Utility Property Plant and Equipment      
Number of nuclear units | unit 2    
Ownership participation agreement      
Public Utility Property Plant and Equipment      
Ownership share, generating capacity (in megawatts) | MW 727    
Total construction costs paid $ 8,300,000    
Proceeds from settlement agreement 1,100,000    
Ownership participation agreement | Minimum      
Public Utility Property Plant and Equipment      
Additional capital costs incurred 10,000    
Ownership participation agreement | Maximum      
Public Utility Property Plant and Equipment      
Additional capital costs incurred 15,000    
Global Amendments to Term Sheet | Jointly Owned Nuclear Power Plant | Georgia Power      
Public Utility Property Plant and Equipment      
Total construction costs paid $ 437,000