UNITED STATES

SECURITIES AND EXCHANGE COMMISSION

Washington, D.C. 20549

 

 

Form 6-K

 

 

REPORT OF FOREIGN PRIVATE ISSUER

PURSUANT TO RULE 13a-16 OR 15d-16

UNDER THE SECURITIES EXCHANGE ACT OF 1934

April 18, 2024

 

 

BHP GROUP LIMITED

(ABN 49 004 028 077)

(Exact name of Registrant as specified in its charter)

 

 

VICTORIA, AUSTRALIA

(Jurisdiction of incorporation or organisation)

171 COLLINS STREET, MELBOURNE,

VICTORIA 3000 AUSTRALIA

(Address of principal executive offices)

 

 

Indicate by check mark whether the registrant files or will file annual reports under cover of Form 20-F or Form 40-F: ☒ Form 20-F ☐ Form 40-F

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(1): ☐

Indicate by check mark if the registrant is submitting the Form 6-K in paper as permitted by Regulation S-T Rule 101(b)(7): ☐

Indicate by check mark whether the registrant by furnishing the information contained in this Form is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the Securities Exchange Act of 1934: ☐ Yes ☒ No

If “Yes” is marked, indicate below the file number assigned to the registrant in connection with Rule 12g3-2(b):  n/a

 

 

 


 

LOGO          18 April 2024

Operational review for the nine months ended 31 March 2024

Solid operational performance in copper, iron ore and energy coal.

“We remain on track to meet copper, iron ore and energy coal production for the year. Copper volumes have increased by 10 per cent reflecting strong performance and additional tonnes from Copper South Australia, record year-to-date performance from Spence, and improved grades and production at Escondida.

“Western Australia Iron Ore, the lowest cost iron ore producer globally, delivered another consistent period of production despite heavy rainfall. We continue to invest in improvements to our rail and port operations, which are essential for growth in the medium term to 305 million tonnes per annum and beyond.

“At our BMA metallurgical coal operations in Queensland, significant wet weather including the impact of two tropical cyclones and operational challenges impacted production and unit costs, and we have revised guidance for the year. We successfully completed the sale of the Blackwater and Daunia mines on 2 April for a total of up to US$4.1 bn (100%).

“In Canada, the Jansen Stage 1 project remains ahead of its initial schedule and is now 44 per cent complete. In Western Australia, we expect to announce a decision on the future of our nickel business in the coming months, where efforts to optimise operations and preserve value are underway.”

 

   Mike Henry
   BHP Chief Executive Officer

Summary

 

  
   

Operational performance

  

Portfolio

Copper production increased 10%

  

Completed sale of Blackwater and Daunia

Increased copper production driven by record production at Spence, strong operational performance at Copper South Australia (and the contribution from Prominent Hill and Carrapateena), and improved performance and grade at Escondida.

 

  

We completed the strategic reshaping of our metallurgical coal business with the divestment of BHP Mitsubishi Alliance’s (BMA) Blackwater and Daunia mines to Whitehaven Coal on 2 April for a total cash consideration of up to US$4.1 bn (100%).

 

FY24 production guidance for BMA has been lowered to 21.5 – 22.5 Mt (43 – 45 Mt at 100%). Other updates to FY24 production guidance are reflected in the table below. FY24 unit cost guidance1 for BMA has been increased to US$119/t – US$125/t.

 

  

BMA now has a more focused operational footprint and a greater portion of higher quality metallurgical coal (>85%) which is expected to achieve higher relative margins in a decarbonising world.

 

   

ESG

  

Governance

MSCI upgrade

  

Board update

In March 2024, ESG ratings provider MSCI upgraded BHP’s overall company score based on their assessment of performance under the Social Pillar. This reflects the progress made in Brazil, including in negotiations, and our commitment to deliver full and fair remediation and compensation.    In March, we announced the appointment of Ross McEwan and Don Lindsay as Non-executive Directors, effective 3 April 2024 and 1 May 2024 respectively. We also announced the retirement of Ian Cockerill as a Non-executive Director, effective 4 April 2024.

 

         
 Production    Quarter performance     YTD performance     FY24 production guidance         
   
     Q3 FY24      v Q2 FY24     v Q3 FY23    

YTD Mar

FY24

    

v YTD Mar

FY23

    Previous     Current        
                 

Copper (kt)

     465.9        7     15     1,360.3        10     1,720 – 1,910       1,720 –1,910          
   

Escondida (kt)

     288.2        13     15     816.1        7     1,080 – 1,180       1,080 –1,180       Unchanged  
   

Pampa Norte (kt)

     61.6        3     (16 %)      199.7        (9 %)      210 – 250 i      210 – 250 i      Upper end  
   

Copper South Australia (kt)

     79.0        (4 %)      53     232.7        49     310 – 340       310 – 340       Unchanged  
   

Antamina (kt)

     33.9        (14 %)      15     105.6        4     120 – 140       120 – 140     Unchanged  
   

Carajás (kt)

     3.2        78       6.2            -       -       -  
                 

Iron ore (Mt)

     61.5        (7 %)      3     190.5        (1 %)      254 – 264.5       254 – 264.5          
   

WAIO (Mt)

     60.3        (6 %)      3     186.8        (1 %)      250 – 260       250 – 260       Unchanged  
   

WAIO (100% basis) (Mt)

     68.1        (6 %)      3     210.2        (1 %)      282 – 294       282 – 294       Unchanged  
   

Samarco (Mt)

     1.2        (10 %)      12     3.7        13     4 – 4.5       4 – 4.5       Upper end  
                 

Metallurgical coal – BMA (Mt)

     6.0        6     (13 %)      17.4        (16 %)      23 – 25       21.5 – 22.5       Lowered  
   

BMA (100% basis) (Mt)

     12.1        6     (13 %)      34.7        (16 %)      46 – 50       43 – 45       Lowered  
                 

Energy coal – NSWEC (Mt)

     4.1        8     5     11.6        23     13 – 15       13 – 15       Upper end  
   

Nickel – Western Australia Nickel (kt)

     18.8        (4 %)      (4 %)      58.6        1     77 – 87       77 – 87       Lower half  

 

Note:

changes made to FY24 production guidance since the Q2 FY24 Operational review are shown in italics.

 

i

Production guidance for FY24 is for Spence only and excludes Cerro Colorado which produced 11 kt before ceasing production on 9 November 2023.


BHP | Operational Review for the nine months ended 31 March 2024

 

Segment and asset performance | FY24 YTD v FY23 YTD

 

 

LOGO

 

  

 

Further information in Appendix 1

 

Detailed production and sales information for all operations in Appendix 2

 

Copper

 

  

Production

 

1,360 kt LOGO 10%

 

YTD Mar FY23 1,240 kt

 

FY24e 1,720 – 1,910 kt

 

Average realised price

 

US$3.72/lb LOGO 5%

 

HY24 US$3.66/lb

  

Total copper production increased by 10% to 1,360 kt. Copper production guidance for FY24 remains unchanged at between 1,720 and 1,910 kt.

 

Escondida 816 kt LOGO 7% (100% basis)

 

Increased production was primarily due to a higher concentrator feed grade of 0.85%, increasing from 0.79%, as mining progressed into areas of high grade ore as planned following the implementation of measures to manage geotechnical events. Concentrator feed grade for FY24 is expected to be between 0.85% and 0.90%, with 0.92% grade achieved in Q3 FY24. Production guidance for FY24 remains unchanged at between 1,080 and 1,180 kt.

 

Pampa Norte 200 kt LOGO 9%

 

   Spence production increased by 3% to a nine-month record of 189 kt, driven by improved concentrator throughput and higher recoveries. Record concentrate production was partially offset by lower cathode production, in line with an expected decline in stacked feed grade. The concentrator plant modifications which commenced in August 2022 are expected to be completed in FY24.
   In March 2024, Spence achieved fully autonomous mine haulage operations (ahead of the Q4 FY24 target date) and has deployed a total of 33 autonomous trucks.
   FY24 production for Spence is expected to be at the upper end of the guidance range of between 210 and 250kt.
   Cerro Colorado entered temporary care and maintenance in December 2023, after producing 11 kt for the period.
  

Copper South Australia 233 kt LOGO 49%

   Production increased by 49% due to the addition of volumes this year from Prominent Hill and Carrapateena, and strong underlying operational performance at Olympic Dam including the highest quarter of material mined in over 10 years in Q3 FY24. Strong smelter performance at Olympic Dam was supported by ongoing transfers of concentrate from Prominent Hill and initial transfers from Carrapateena in Q3 FY24, for processing to higher margin cathode. Crusher 2 at Carrapateena was commissioned in Q3 FY24 and remains on track to ramp up in Q4 FY24.
   Production guidance for FY24 remains unchanged at between 310 and 340 kt.
   We are continuing exploration drilling across the Copper South Australia province to enhance our resource knowledge in support of our growth studies. At Oak Dam, we are progressing the external approval process for an underground access decline to enable faster and lower cost resource definition drilling of the mineral deposit, and we expect to be able to provide an Inferred Mineral Resource for Oak Dam later this calendar year.
  

Other copper

   At Antamina, copper production increased by 4% to 106 kt, while zinc production was 2% higher at 88 kt, both as a result of higher throughput offsetting planned lower concentrator feed grades. Production guidance remains unchanged for FY24, with copper production of between 120 and 140 kt, and zinc production of between 85 and 105 kt.
   Carajás produced 6.2 kt of copper and 4.1 troy koz of gold. In Q3 FY24 operations continued to ramp back up, and shipments also resumed, following the temporary stoppage of operations between August and October 2023 due to a geotechnical event.

 

2


BHP | Operational Review for the nine months ended 31 March 2024

 

Iron ore

 

Production

 

190 Mt LOGO 1%

 

YTD Mar FY23 192 Mt

FY24e 254 – 264.5 Mt

 

Average realised price

 

US$104.53/wmt LOGO 3%

 

HY24 US$103.70/wmt

  

Total iron ore production decreased by 1% to 190 Mt. Production guidance for FY24 remains unchanged at between 254 and 264.5 Mt.

 

WAIO 187 Mt LOGO 1% | 210 Mt (100% basis)

 

Production was marginally lower due to heavy rainfall throughout Q3 FY24, the continued tie-in activity for the Rail Technology Programme (RTP1), the impacts of the ongoing ramp up of the Central Pilbara hub (South Flank and Mining Area C) and a bushfire near Yandi.

 

South Flank remains on track to ramp up to full production capacity of 80 Mtpa (100% basis) by the end of FY24. The Port Debottlenecking Project (PDP1) was commissioned in December 2023 and ramp up remains on track to be completed in CY24.

 

Production guidance for FY24 remains unchanged at between 250 and 260 Mt (282 and 294 Mt on a 100% basis).

 

Samarco 3.7 Mt LOGO 13% | 7.4 Mt (100% basis)

 

Production increased as a result of higher concentrator throughput. FY24 production is expected to be at the upper end of the 4 – 4.5 Mt guidance range.

 

Coal

 

Metallurgical coal

 

  

Production

 

17.4 Mt LOGO 16%

 

YTD Mar FY23 20.5 Mt

 

FY24e 21.5 – 22.5 Mt

 

Average realised price

 

US$272.09/t LOGO 6%

 

HY24 US$266.43/t

  

BMA 17.4 Mt LOGO 16% | 34.7 Mt (100% basis)

 

Following the tragic fatality of a team member in January 2024, BMA operations were suspended for 24 hours while a safety stop was implemented across all mines, and for a further 3.5 days at Saraji.

 

Production has been impacted by increased planned maintenance, an extended longwall move at Broadmeadow as well as increased stripping to improve supply chain stability at our open cut operations to restore depleted inventory positions arising from extended weather impacts and labour constraints over recent years. Our focus on restoring depleted inventory will continue into CY25.

 

Despite improved production in Q3 FY24, the impacts of higher than planned wet weather, including two tropical cyclones in the region, and the temporary suspension of operations following the fatality at Saraji have impacted our FY24 production estimates. Production for FY24 is now expected to be between 21.5 and 22.5 Mt (43 and 45 Mt on a 100% basis). This has been lowered from 23 – 25 Mt (46 – 50 Mt on a 100% basis).

 

As a result, unit cost guidance for FY241 has increased to between US$119/t and US$125/t, from US$110 – US$116/t.

Energy coal

 

  

Production

 

11.6 Mt LOGO 23%

 

YTD Mar FY23 9.4 Mt

 

FY24e 13 – 15 Mt

 

Average realised price

 

US$120.97/t LOGO 6%

 

HY24 US$123.29/t

  

NSWEC 11.6 Mt LOGO 23%

 

Increased production as a result of continued strong operating performance as improved weather conditions enabled an uplift in truck productivity. Domestic sales under the NSW Government Coal Market Price Emergency (Directions for Coal Mines) Notice commenced in Q4 FY23, which has resulted in a lower proportion of washed coal and further contributed to the higher volumes.

 

Production for FY24 is expected to be at the upper end of the guidance range of between 13 and 15 Mt.

 

The approval process in relation to the modification request submitted to the NSW Government to extend mining approval to 30 June 2030 will continue into FY25. The approval would allow NSWEC to continue mining beyond its current mining consent that expires in 2026 and proceed with a managed process to cease mining at the asset by the end of FY30.

 

3


BHP | Operational Review for the nine months ended 31 March 2024

 

Group & Unallocated
Nickel  
Production   Western Australia Nickel 59 kt LOGO 1%

59 kt LOGO 1%

 

YTD Mar FY23 58 kt

  Production increased, despite significant wet weather impacts in Q3 FY24. Production for FY24 is expected to be in the lower half of the guidance range of between 77 and 87 kt.

 

FY24e 77 – 87 kt

 

Average realised price

 

US$18,104/t LOGO 1%

 

  As announced in our HY24 results in February 2024, we continue to review our plans for Western Australia Nickel with a focus on preserving cash. This includes optimising operations and maintenance schedules, reviewing capital plans, and reducing contractor spend and equipment hire. Our review also includes assessing the potential to place Nickel West into a period of care and maintenance and the phasing and capital spend for the development of the West Musgrave project. We expect to provide an update on the longer-term future of Western Australia Nickel by the FY24 results in August 2024.
HY24 US$18,602/t  

Quarterly performance | Q3 FY24 v Q2 FY24

 

 

Copper

 

     

 

Iron ore

 

   

466 kt LOGO 7%

 

Q2 FY24 437 kt

 

Higher concentrator grade at Escondida and concentrator throughput at Spence, partially offset by lower volumes at Copper South Australia due to planned maintenance and the commissioning of Crusher 2 at Carrapateena in Q3 FY24.

 

 

61 Mt LOGO 7%

 

Q2 FY24 66 Mt

 

Lower production at WAIO as a result of wet weather, a bushfire near Yandi and the impacts of the RTP1 tie-in activity, partially offset by improved underlying mine performance.

 

 

Metallurgical coal

 

 

 

Energy coal

 

6.0 Mt LOGO 6%

 

Q2 FY24 5.7 Mt

 

Production increased due to improved strip ratio and yield despite unfavourable weather. Operations were temporarily suspended for safety stops following the fatality of a team member at Saraji.

 

 

4.1 Mt LOGO 8%

 

Q2 FY24 3.9 Mt

  Increased production as a result of favourable mining sequence, strong production performance and a reduced proportion of washed coal.

 

Nickel

           

 

19 kt LOGO 4%

 

Q2 FY24 20 kt

 

 

Lower volumes due to planned maintenance at the Kwinana Refinery and a severe weather event in March.

 

       

The following footnotes apply to this Operational Review:

 

1

FY24 unit cost guidance is based on exchange rate of AUD/USD 0.67.

 

4


BHP | Operational Review for the nine months ended 31 March 2024

 

Appendix 1

Average realised prices1

 

        Q3 FY24        YTD Mar FY24        Q3 FY24 v
Q2 FY24
       YTD Mar FY24 v
H1 FY24
 

 Copper (US$/lb)2

       3.85          3.72          5        5

 Iron ore (US$/wmt, FOB)

       106.30          104.53          (3 )%         3

 Metallurgical coal (US$/t)

       281.51          272.09          (4 )%         6

Hard coking coal (US$/t)3

       293.94          281.98          (4 )%         7

Weak coking coal (US$/t)3

       208.91          206.38          (2 )%         2

 Thermal coal (US$/t)4

       116.11          120.97          (4 )%         (6 )% 

 Nickel metal (US$/t)5

       16,581          18,104          (1 )%         (1 )% 

 

1

Based on provisional, unaudited estimates. Prices exclude sales from equity accounted investments, third party product and internal sales, and represent the weighted average of various sales terms (for example: FOB, CIF and CFR), unless otherwise noted. Includes the impact of provisional pricing and finalisation adjustments.

 

2

Does not include sales from assets acquired through the purchase of OZL.

 

3

Hard coking coal (HCC) refers generally to those metallurgical coals with a Coke Strength after Reaction (CSR) of 35 and above, which includes coals across the spectrum from Premium Coking to Semi Hard Coking coals, while weak coking coal (WCC) refers generally to those metallurgical coals with a CSR below 35.

 

4

Export sales only. Includes thermal coal sales from metallurgical coal mines.

 

5

Relates to refined nickel metal only, excludes intermediate products and nickel sulphate.

Current year unit cost guidance

 

       

Previous

 

FY24 guidance1

      

Current

 

FY24 guidance1

           

 Escondida unit cost (US$/lb)2

       1.40 –1.70          1.40 – 1.70          Unchanged  

 Spence unit cost (US$/lb)

       2.00 – 2.30          2.00 – 2.30          Unchanged  

 WAIO unit cost (US$/t)

       17.40 – 18.90          17.40 – 18.90          Unchanged  

 BMA unit cost (US$/t)

       110 – 116          119 – 125          Increased  

 

1

FY24 unit cost guidance is based on exchange rates of AUD/USD 0.67 and USD/CLP 810.

 

2

Escondida unit costs for FY24 onwards exclude revenue-based government royalties.

Medium term guidance

 

       

Production

 

guidance

    

Unit cost

 

guidance1

 

 Escondida2

       1,200 –1,300 kt        US$1.30 – $1.60/lb3  

 Spence4

       ~250 kt           

 WAIO (100% basis)

       >305 Mt        <US$17/t  

 

1

Medium term unit cost guidance is based on exchange rates of AUD/USD 0.67 and USD/CLP 810.

 

2

Medium term refers to an average across FY25 and FY26.

 

3

Escondida unit costs for FY24 onwards exclude revenue-based government royalties.

 

4

Average of 250 ktpa over five years on the basis that remediation of the previously identified TSF anomalies does not impact operations.

Major projects

 

 Commodity    Project and ownership   Project scope / capacity    Capital
expenditure
US$M
     First
production
target date
     Progress  

 Potash

   Jansen Stage 1
(Canada)
100%
  Design, engineering and construction of an underground potash mine and surface infrastructure, with capacity to produce 4.15 Mtpa.      5,723        End-CY26       

Project is 44

complete


 

 Potash

   Jansen Stage 2
(Canada)
100%
  Development of additional mining districts, completion of the second shaft hoist infrastructure, expansion of processing facilities and addition of rail cars to facilitate production of an incremental 4.36 Mtpa.      4,859        FY29       

Approval

announced

October 2023

 

 

 

Exploration

Minerals exploration and evaluation expenditure was US$311 m for YTD March 24 (YTD Mar 23: US$239 m) of which US$267 m was expensed (YTD Mar 23: US$196 m).

 

5


BHP | Operational Review for the nine months ended 31 March 2024

 

Appendix 2

 

            Production                 Sales  
            Quarter ended           Year to date                 Quarter ended           Year to date  
            Mar     Jun     Sep     Dec     Mar           Mar     Mar     Var                 Mar     Jun     Sep     Dec     Mar           Mar     Mar     Var  
            2023     2023     2023     2023     2024           2024     2023     %                 2023     2023     2023     2023     2024           2024     2023     %  

Group production and sales summary

 

                     

By commodity

 

                     

Metals production is payable metal unless otherwise noted.

 

                                             

Throughout this report figures in italics indicate that this figure has been adjusted since it was previously reported.

 

                                                                                                       

Copper

  Payable metal in concentrate   kt     262.4       310.7       317.3       308.7       339.1             965.1       807.2       20         268.4       323.1       298.0       316.5       281.6         896.1       801.4       12
  Escondida   kt     200.8       220.5       221.3       207.7       239.2         668.2       612.2       9         197.3       220.3       209.5       211.7       204.0         625.2       610.0       2
  Pampa Norte   kt     32.0       32.2       38.8       32.6       39.5         110.9       93.1       19         38.7       38.6       31.3       34.9       26.9         93.1       86.7       7
  Copper South Australia   kt             19.9       23.5       27.4       23.3         74.2                                   27.6       22.2       31.6       17.1         70.9                  
  Antamina   kt     29.6       36.5       32.5       39.2       33.9         105.6       101.9       4         32.4       34.5       32.8       38.3       31.3         102.4       104.7       (2 )% 
  Carajás   kt             1.6       1.2       1.8       3.2         6.2                                   2.1       2.2       -       2.3         4.5                  
  Cathode   kt     143.5       165.5       139.7       128.7       126.8         395.2       433.1       (9 )%          130.3       179.9       131.9       137.6       120.1         389.6       420.4       (7 )% 
  Escondida   kt     50.8       72.5       52.0       46.9       49.0         147.9       150.1       (1 )%          43.8       78.0       49.2       52.2       44.3             145.7       143.2       2
  Pampa Norte   kt     41.0       36.3       39.5       27.2       22.1         88.8       127.2       (30 )%          36.0       42.4       36.6       31.1       22.1         89.8       124.0       (28 )% 
  Copper South Australia   kt     51.7       56.7       48.2       54.6       55.7         158.5       155.8       2         50.5       59.5       46.1       54.3       53.7         154.1       153.2       1
    Total   kt     405.9       476.2       457.0       437.4       465.9         1,360.3       1,240.3       10         398.7       503.0       429.9       454.1       401.7         1,285.7       1,221.8       5

Lead

  Payable metal in concentrate   t     169       146       96       105       -         201       511       (61 )%          181       143       154       91       108         353       402       (12 )% 
    Antamina   t     169       146       96       105       -         201       511       (61 )%          181       143       154       91       108         353       402       (12 )% 

Zinc

  Payable metal in concentrate   t     23,612       38,822       35,669       33,475       18,409         87,553       86,226       2         25,851       37,629       33,912       37,092       17,559         88,563       88,798       0
    Antamina   t     23,612       38,822       35,669       33,475       18,409         87,553       86,226       2         25,851       37,629       33,912       37,092       17,559         88,563       88,798       0

Gold

  Payable metal in concentrate   troy oz     57,106       96,655       89,024       94,794       79,284         263,102       153,140        72         57,106       108,552       87,703       98,969       70,493         257,165       153,140       68
  Escondida   troy oz     48,954       53,503       48,063       48,633       38,955         135,651       135,592       0         48,954       53,503       48,063       48,633       38,955         135,651       135,592       0
  Pampa Norte   troy oz     8,152       9,263       3,931       2,854       1,819         8,604       17,548       (51 )%          8,152       9,263       3,931       2,854       1,819         8,604       17,548       (51 )% 
  Copper South Australia   troy oz             32,736       36,228       42,051       36,427         114,706                                   44,098       34,176       47,482       28,136         109,794                  
  Carajás   troy oz             1,153       802       1,256       2,083         4,141                                   1,688       1,533       —        1,583         3,116                  
  Refined gold   troy oz     49,086       46,479       53,028       55,828       49,128         157,984       139,550       13         47,300       49,182       54,036       55,349       41,710         151,095       138,742       9
  Copper South Australia   troy oz     49,086       46,479       53,028       55,828       49,128         157,984       139,550       13         47,300       49,182       54,036       55,349       41,710         151,095       138,742       9
    Total   troy oz     106,192       143,134       142,052       150,622       128,412         421,086       292,690       44         104,406       157,734       141,739       154,318       112,203         408,260       291,882       40

Silver

  Payable metal in concentrate   troy koz     2,556       2,592       2,582       3,074       2,620         8,276       7,886       5         2,523       2,409       2,527       2,938       2,431         7,896       7,605       4
  Escondida   troy koz     1,346       1,008       1,168       1,401       1,328         3,897       4,066       (4 )%          1,346       1,008       1,168       1,401       1,328         3,897       4,066       (4 )% 
  Pampa Norte   troy koz     409       412       356       388       327         1,071       906       18         409       412       356       388       327         1,071       906       18
  Copper South Australia   troy koz             201       260       310       252         822                                   242       258       364       189         811                  
  Antamina   troy koz     801       971       798       975       713         2,486       2,914       (15 )%          768       747       745       785       587         2,117       2,633       (20 )% 
  Refined silver   troy koz     277       256       261       221       248         730       833       (12 )%          307       270       219       222       188         629       860       (27 )% 
  Copper South Australia   troy koz     277       256       261       221       248         730       833       (12 )%          307       270       219       222       188         629       860       (27 )% 
    Total   troy koz     2,833       2,848       2,843       3,295       2,868         9,006       8,719       3         2,830       2,679       2,746       3,160       2,619         16,421       16,070       2

Uranium

  Payable metal in concentrate   t     833       813       825       986       863         2,674       2,593       3         683       1,275       481       895       394         1,770       2,082       (15 )% 
    Copper South Australia   t     833       813       825       986       863         2,674       2,593       3         683       1,275       481       895       394         1,770       2,082       (15 )% 

Molybdenum

  Payable metal in concentrate   t     636       666       612       481       824         1,917       1,496       28         789       594       564       468       677         1,709       1,578       8
  Pampa Norte   t     407       333       329       145       203         677       657       3         492       367       303       162       219         684       733       (7 )% 
    Antamina   t     229       333       283       336       621         1,240       839       48         297       227       261       306       458         1,025       845       21

Iron ore

  Western Australia Iron Ore (WAIO)   kt     58,725       64,074       62,004       64,460       60,299         186,763       188,457       (1 )%          59,204       62,926       64,180       62,606       61,868         188,654       185,957       1
  Samarco   kt     1,048       1,221       1,231       1,302       1,174         3,707       3,291       13         1,111       1,160       1,136       1,329       1,258         3,723       3,354       11
    Total   kt     59,773       65,295       63,235       65,762       61,473         190,470       191,748       (1 )%          60,315       64,086       65,316       63,935       63,126         192,377       189,311       2

Metallurgical coal¹

  BHP Mitsubishi Alliance (BMA)   kt     6,929       8,477       5,601       5,717       6,035         17,353       20,543       (16 )%          6,186       8,876       5,325       5,706       6,359         17,390       19,695       (12 )% 

Energy coal

  NSW Energy Coal (NSWEC)   kt     3,934       4,765       3,613       3,855       4,149         11,617       9,407       23         3,667       4,894       3,307       4,250       3,932         11,489       8,970       28

Nickel

  Western Australia Nickel   kt     19.6       22.0       20.2       19.6       18.8         58.6       58.0       1         19.6       23.4       18.9       20.0       18.8         57.7       58.7       (2 )% 

Cobalt

  Western Australia Nickel   t     175       246       192       182       179         553       506       9         175       246       192       110       179         481       506       (5 )% 

1 Includes BMA thermal coal sales.

 

6


BHP | Operational Review for the nine months ended 31 March 2024

 

           

 

Production

 

       

 

Sales

 

 
            Quarter ended         Year to date             Quarter ended         Year to date  
            Mar
2023
    Jun
2023
    Sep
2023
    Dec
2023
    Mar
2024
        Mar
2024
    Mar
2023
   

Var

%

            Mar
2023
    Jun
2023
    Sep
2023
    Dec
2023
    Mar
2024
        Mar
2024
    Mar
2023
   

Var

%

 

Production and sales

                                         

By asset

                                         

Copper

                                         
 

Metals production is payable metal unless otherwise noted.

                                         

Escondida, Chile¹

  BHP interest 57.5%

 

                                     
  Material mined   kt     106,170       95,451       87,462       95,168       103,872         286,502       318,405       (10)%                        
  Concentrator throughput   kt     33,309       30,750       33,332       34,752       31,653         99,737       100,114       0%                        
  Average copper grade - concentrator   %     0.78%       0.93%       0.85%       0.78%       0.92%         0.85%       0.79%       7%                        
  Production ex mill   kt     210.0       228.9       225.7       217.6       238.6         681.9       637.4       7%                                                                        
  Payable copper   kt     200.8       220.5       221.3       207.7       239.2         668.2       612.2       9%           197.3       220.3       209.5       211.7       204.0         625.2       610.0       2%  
  Copper cathode (EW)   kt     50.8       72.5       52.0       46.9       49.0         147.9       150.1       (1)%           43.8       78.0       49.2       52.2       44.3         145.7       143.2       2%  
  Oxide leach   kt     14.7       29.3       17.5       17.0       14.4         48.9       47.5       3%                        
  Sulphide leach   kt     36.1       43.2       34.5       29.9       34.6         99.0       102.6       (4)%                        
  Total copper   kt     251.6       293.0       273.3       254.6       288.2         816.1       762.3       7%           241.1       298.3       258.7       263.9       248.3         770.9       753.2       2%  
  Payable gold concentrate   troy oz     48,954       53,503       48,063       48,633       38,955         135,651       135,592       0%           48,954       53,503       48,063       48,633       38,955         135,651       135,592       0%  
    Payable silver concentrate   troy koz     1,346       1,008       1,168       1,401       1,328         3,897       4,066       (4)%           1,346       1,008       1,168       1,401       1,328         3,897       4,066       (4)%  

1 Shown on a 100% basis.

                                         

Pampa Norte, Chile

  BHP interest 100%

 

                                     

Copper

  Payable metal in concentrate   kt     32.0       32.2       38.8       32.6       39.5         110.9       93.1       19%           38.7       38.6       31.3       34.9       26.9         93.1       86.7       7%  
  Cathode   kt     41.0       36.3       39.5       27.2       22.1         88.8       127.2       (30)%           36.0       42.4       36.6       31.1       22.1         89.8       124.0       (28)%  
    Total copper   kt     73.0       68.5       78.3       59.8       61.6         199.7       220.3       (9)%           74.7       81.0       67.9       66.0       49.0         182.9       210.7       (13)%  

Gold

      troy oz     8,152       9,263       3,931       2,854       1,819         8,604       17,548       (51)%           8,152       9,263       3,931       2,854       1,819         8,604       17,548       (51)%  

Silver

      troy koz     409       412       356       388       327         1,071       906       18%           409       412       356       388       327         1,071       906       18%  

Molybdenum

      t     407       333       329       145       203         677       657       3%           492       367       303       162       219         684       733       (7)%  
                                                                                                                         

Cerro Colorado¹

                                           
  Material mined   kt     172       145       -       -       -         -       3,934       (100)%                        
  Ore stacked   kt     3,567       3,928       154       -       -         154       12,059       (99)%                        
  Average copper grade - stacked   %     0.57%       0.53%       0.58%       -       -         0.58%       0.56%       4%                                                                        
  Copper cathode (EW)   kt     12.0       12.2       9.5       1.6       -         11.1       37.0       (70)%           10.9       14.1       8.8       3.7       -         12.5       36.4       (66)%  
                                                                                                                         

Spence

                                           
  Material mined   kt     24,858       25,622       27,654       25,973       15,968         69,595       78,794       (12)%                        
  Ore stacked   kt     4,947       5,625       5,113       4,744       6,008         15,865       15,679       1%                        
  Average copper grade - stacked   %     0.60%       0.58%       0.60%       0.59%       0.56%         0.58%       0.66%       (11)%                        
  Concentrator throughput   kt     7,290       6,927       8,473       7,151       8,055         23,679       21,325       11%                        
  Average copper grade - concentrator   %     0.61%       0.61%       0.64%       0.65%       0.64%         0.64%       0.61%       5%                                                                        
  Payable copper   kt     32.0       32.2       38.8       32.6       39.5         110.9       93.1       19%           38.7       38.6       31.3       34.9       26.9         93.1       86.7       7%  
  Copper cathode (EW)   kt     29.0       24.1       30.0       25.6       22.1         77.7       90.2       (14)%           25.1       28.3       27.8       27.4       22.1         77.3       87.6       (12)%  
  Total copper   kt     61.0       56.3       68.8       58.2       61.6         188.6       183.3       3%           63.8       66.9       59.1       62.3       49.0         170.4       174.3       (2)%  
  Payable gold concentrate   troy oz     8,152       9,263       3,931       2,854       1,819         8,604       17,548       (51)%           8,152       9,263       3,931       2,854       1,819         8,604       17,548       (51)%  
  Payable silver concentrate   troy koz     409       412       356       388       327         1,071       906       18%           409       412       356       388       327         1,071       906       18%  
    Payable molybdenum   t     407       333       329       145       203         677       657       3%           492       367       303       162       219         684       733       (7)%  

1 Cerro Colorado entered temporary care and maintenance in December 2023.

 

7


BHP | Operational Review for the nine months ended 31 March 2024

 

             Production                 Sales  
             Quarter ended           Year to date                 Quarter ended           Year to date  
             Mar     Jun     Sep     Dec     Mar           Mar     Mar     Var                 Mar     Jun     Sep     Dec     Mar           Mar     Mar     Var  
             2023     2023     2023     2023     2024         2024     2023     %             2023     2023     2023     2023     2024         2024     2023     %  

Copper (continued)

                                         

Copper South Australia, Australia

  BHP interest 100%

 

                                     

Copper

   Payable metal in concentrate   kt             19.9       26.2       30.6       27.4         84.2                                   27.6       22.2       31.6       17.1         70.9                  
   Cathode   kt     51.7       56.7       48.2       54.6       55.7         158.5       155.8       2%           50.5       59.5       46.1       54.3       53.7         154.1       153.2       1%  
   Total copper   kt     51.7       76.6       74.4       85.2       83.1         242.7       155.8       56%           50.5       87.1       68.3       85.9       70.8         225.0       153.2       47%  
   Payable metal in concentrate transfer to Olympic Dam¹   kt             -       (2.7)       (3.2)       (4.1)         (10.0)                                        
     Net copper   kt     51.7       76.6       71.7       82.0       79.0         232.7       155.8       49%                                                                        

Gold

   Payable metal in concentrate   troy oz             32,736       41,424       48,051       43,209             132,684                                           44,098       34,176       47,482       28,136         109,794                  
   Refined gold   troy oz     49,086       46,479       53,028       55,828       49,128         157,984       139,550       13%           47,300       49,182       54,036       55,349       41,710         151,095       138,742       9%  
   Total gold   troy oz     49,086       79,215       94,452       103,879       92,337         290,668       139,550       108%           47,300       93,280       88,212       102,831       69,846         260,889       138,742       88%  
   Payable metal in concentrate transfer to Olympic Dam¹   troy oz             -       (5,196)       (6,000)       (6,782)         (17,978)                                        
     Net gold   troy oz     49,086       79,215       89,256       97,879       85,555         272,690       139,550       95%                                                                        

Silver

   Payable metal in concentrate   troy koz             201       271       323       282         876                                   242       258       364       189         811                  
   Refined silver   troy koz     277       256       261       221       248         730       833       (12)%           307       270       219       222       188         629       860       (27)%  
   Total silver   troy koz     277       457       532       544       530         1,606       833       93%           307       512       477       586       377         1,440       860       67%  
   Payable metal in concentrate transfer to Olympic Dam¹   troy koz             -       (11)       (13)       (30)         (54)                                        
     Net silver   troy koz     277       457       521       531       500         1,552       833       86%                                                                        

Uranium

       t     833       813       825       986       863         2,674       2,593       3%           683       1,275       481       895       394         1,770       2,082       (15)%  
                                            

Olympic Dam

                                            
   Material mined   kt     2,317       2,356       2,655       2,537       2,747         7,939       6,993       14%                        
   Ore milled   kt     2,433       2,755       2,596       2,634       2,511         7,741       7,690       1%                        
   Average copper grade   %     1.95%       2.00%       1.96%       2.12%       1.96%         2.01%       2.06%       (2)%                        
   Average uranium grade   kg/t     0.59       0.55       0.56       0.62       0.57         0.58       0.58       0%                                                                        
   Copper cathode (ER and EW)   kt     51.7       56.7       48.2       54.6       55.7         158.5       155.8       2%           50.5       59.5       46.1       54.3       53.7         154.1       153.2       1%  
   Refined gold   troy oz     49,086       46,479       53,028       55,828       49,128         157,984       139,550       13%           47,300       49,182       54,036       55,349       41,710         151,095       138,742       9%  
   Refined silver   troy koz     277       256       261       221       248         730       833       (12)%           307       270       219       222       188         629       860       (27)%  
   Payable uranium   t     833       813       825       986       863         2,674       2,593       3%           683       1,275       481       895       394         1,770       2,082       (15)%  
                                            

Prominent Hill²

                                            
   Material mined   kt             661       1,110       1,125       1,094         3,329                                        
   Ore milled   kt             1,228       1,652       1,800       1,473         4,925                                        
   Average copper grade   %             0.77%       0.85%       0.83%       0.86%         0.85%                                        
   Production ex mill   kt             16.3       23.8       23.6       22.3         69.7                                                                                        
   Payable copper   kt             8.2       12.1       12.9       10.9         35.9                                   15.7       8.4       10.6       6.5         25.5                  
   Payable gold concentrate   troy oz             17,432       22,031       25,779       21,019         68,829                                   28,856       15,524       20,045       14,644         50,213                  
   Payable silver concentrate   troy koz             44       63       65       62         190                                   87       53       59       38         150                  
                                            

Carrapateena²

                                            
   Material mined   kt             880       1,201       1,310       1,232         3,743                                        
   Ore milled   kt             856       1,230       1,307       1,226         3,763                                        
   Average copper grade   %             1.52%       1.29%       1.52%       1.52%         1.44%                                        
   Production ex mill   kt             30.1       37.6       49.2       45.9         132.7                                                                                        
   Payable copper   kt             11.7       14.1       17.7       16.5         48.3                                   11.9       13.8       21.0       10.6         45.4                  
   Payable gold concentrate   troy oz             15,304       19,393       22,272       22,190         63,855                                   15,242       18,652       27,437       13,492         59,581                  
     Payable silver concentrate   troy koz             157       208       258       220         686                                   155       205       305       151         661                  

1 Excludes prior year production previously reported and transferred during the period.

2 Production and sales included from 1 May 2023, following the acquisition of OZL on 2 May 2023.

 

8


BHP | Operational Review for the nine months ended 31 March 2024

 

             Production              Sales  
             Quarter ended          Year to date              Quarter ended          Year to date  
            

Mar

2023

    

Jun

2023

    

Sep

2023

    

Dec

2023

    

Mar

2024

        

Mar

2024

    

Mar

2023

    

Var

%

            

Mar

2023

    

Jun

2023

    

Sep

2023

    

Dec

2023

    

Mar

2024

        

Mar

2024

    

Mar

2023

    

Var

%

 

Copper (continued)

                                                         
 

Antamina, Peru

 

BHP interest 33.75%

 

      
 

Material mined

 

kt

     57,939        62,894        63,310        61,539        56,233          181,082        190,554        (5)%                                
  Concentrator throughput  

kt

     12,349        13,897        14,246        14,824        14,312          43,382        40,479        7%                                
  Average head grade - copper  

%

     0.88%        0.88%        0.83%        0.90%        0.83%          0.85%        0.89%        (4)%                                
  Average head grade - zinc  

%

     1.06%        1.25%        1.17%        1.03%        0.68%          0.96%        1.05%        (8)%                                                                                
  Payable copper  

kt

     29.6        36.5        32.5        39.2        33.9          105.6        101.9        4%            32.4        34.5        32.8        38.3        31.3          102.4        104.7        (2)%  
  Payable zinc  

t

     23,612        38,822        35,669        33,475        18,409          87,553        86,226        2%            25,851        37,629        33,912        37,092        17,559          88,563        88,798        0%  
  Payable silver  

troy koz

     801        971        798        975        713          2,486        2,914        (15)%            768        747        745        785        587          2,117        2,633        (20)%  
  Payable lead  

t

     169        146        96        105        -          201        511        (61)%            181        143        154        91        108          353        402        (12)%  
    Payable molybdenum  

t

     229        333        283        336        621          1,240        839        48%            297        227        261        306        458          1,025        845        21%  
                                                           
 

Carajás, Brazil¹

 

BHP interest 100%

 

      
  Material mined  

kt

              103        74        115        163          352                                                  
  Ore milled  

kt

              100        70        119        163          352                                                  
  Average copper grade  

%

              1.71%        1.91%        1.69%        1.93%          1.84%                                                  
  Production ex mill  

kt

              6.6        5.2        7.6        12.9          25.7                                                                                                  
  Payable copper  

kt

              1.6        1.2        1.8        3.2          6.2                                       2.1        2.2        -        2.3          4.5                    
    Payable gold concentrate  

troy oz

              1,153        802        1,256        2,083          4,141                                       1,688        1,533        -        1,583          3,116                    

1 Production and sales included from 1 May 2023, following the acquisition of OZL on 2 May 2023.

 

                             
                             
                             

Iron ore

                                                         

Iron ore production and sales are reported on a wet tonnes basis.

 

                             
 

WAIO, Australia

 

BHP interest 85%

 

      
  Newman Joint Venture  

kt

     11,925        14,795        13,234        15,468        15,032          43,734        42,150        4%                                
  Area C Joint Venture  

kt

     25,284        28,818        25,804        26,074        24,920          76,798        78,557        (2)%                                
  Yandi Joint Venture  

kt

     4,941        5,359        3,150        4,978        4,434          12,562        16,051        (22)%                                
  Jimblebar¹  

kt

     16,575        15,102        19,816        17,940        15,913          53,669        51,699        4%                                
  Total  

kt

     58,725        64,074        62,004        64,460        60,299          186,763        188,457        (1)%                                
  Total (100%)  

kt

     66,163        72,717        69,448        72,670        68,131          210,249        212,590        (1)%                                                                                
  Lump  

kt

                                   18,021        20,022        20,969        19,176        19,175          59,320        57,957        2%  
  Fines  

kt

                                   41,183        42,904        43,211        43,430        42,693          129,334        128,000        1%  
  Total  

kt

                                   59,204        62,926        64,180        62,606        61,868          188,654        185,957        1%  
    Total (100%)  

kt

                                                                                   66,580        71,172        71,748        70,340        69,775          211,863        209,544        1%  

1 Shown on a 100% basis. BHP interest in saleable production is 85%.

 

                             
                                        
 

Samarco, Brazil

 

BHP interest 50%

 

      
    Total  

kt

     1,048        1,221        1,231        1,302        1,174          3,707        3,291        13%            1,111        1,160        1,136        1,329        1,258          3,723        3,354        11%  

 

9


BHP | Operational Review for the nine months ended 31 March 2024

 

             Production              Sales  
             Quarter ended          Year to date              Quarter ended          Year to date  
            

Mar

2023

     Jun
2023
    

Sep

2023

    

Dec

2023

    

Mar

2024

        

Mar

2024

    

Mar

2023

    

Var

%

            

Mar

2023

    

Jun

2023

    

Sep

2023

    

Dec

2023

    

Mar

2024

        

Mar

2024

    

Mar

2023

    

Var

%

 

Coal

                                                           
 

Coal production is reported on the basis of saleable product.

 

 

                             

BMA, Australia

  BHP interest 50%

 

            
 
  Blackwater   kt      1,107        1,505        1,295        1,182        1,070          3,547        3,550        0%                                
 
  Goonyella   kt      2,185        2,348        827        1,736        1,824          4,387        5,962        (26)%                                
 
  Peak Downs   kt      1,251        1,424        1,121        846        1,012          2,979        4,056        (27)%                                
 
  Saraji   kt      1,007        1,326        1,010        701        759          2,470        3,270        (24)%                                
 
  Daunia   kt      607        617        545        431        524          1,500        1,372        9%                                
 
  Caval Ridge   kt      772        1,257        803        821        846          2,470        2,333        6%                                
 
  Total¹   kt      6,929        8,477        5,601        5,717        6,035          17,353        20,543        (16)%                                
 
  Total (100%)   kt      13,858        16,954        11,202        11,434        12,070          34,706        41,086        (16)%                                                                                
 
  Coking coal   kt                                    5,372        7,448        4,497        4,756        5,410          14,663        16,859        (13)%  
 
  Weak coking coal   kt                                    710        1,064        529        752        927          2,208        2,037        8%  
 
  Thermal coal   kt                                    104        364        299        198        22          519        799        (35)%  
 
  Total   kt                                    6,186        8,876        5,325        5,706        6,359          17,390        19,695        (12)%  
 
    Total (100%)   kt                                                                                      12,372        17,752        10,650        11,412        12,718          34,780        39,390        (12)%  
 

1 Production figures include some thermal coal.

 

 

                             
 

NSWEC, Australia

  BHP interest 100%

 

            
 
  Export   kt                                    3,667        4,693        3,087        3,942        3,558          10,587        8,970        18%  
 
  Domestic¹   kt                                       201        220        308        374          902        
 
    Total   kt      3,934        4,765        3,613        3,855        4,149            11,617        9,407        23%            3,667        4,894        3,307        4,250        3,932          11,489        8,970        28%  
 

1 Domestic sales are made under the NSW Government Coal Market Price Emergency (Directions for Coal Mines) Notice 2023.

                           
 

 

Other

                                                           
 

Nickel production is reported on the basis of saleable product.

 

                             
 

Western Australia Nickel, Australia

  BHP interest 100%

 

            
 

Mt Keith

  Nickel concentrate   kt      38.8        44.5        42.7        43.8        32.4          118.9        121.0        (2)%                                
 
    Average nickel grade   %      16.5        16.2        16.7        16.8        15.2          16.3        16.3        0%                                
 

Leinster

  Nickel concentrate   kt      68.4        71.1        66.0        63.4        60.3          189.7        183.1        4%                                
 
    Average nickel grade   %      8.6        8.5        8.1        8.0        7.8          8.0        9.3        (14)%                                                                                
 
  Refined nickel¹   kt      13.2        13.1        13.8        12.6        8.8          35.2        41.5        (15)%            13.0        13.1        13.2        13.0        8.6          34.8        41.3        (16)%  
 
  Nickel sulphate²   kt      0.9        0.7        0.9        0.7        1.0          2.6        2.5        4%            0.9        0.8        0.8        0.7        0.8          2.3        2.2        5%  
 
  Intermediates and nickel by-products³   kt      5.5        8.2        5.5        6.3        9.0          20.8        14.0        49%            5.7        9.5        4.9        6.3        9.4          20.6        15.2        36%  
 
  Total nickel   kt      19.6        22.0        20.2        19.6        18.8          58.6        58.0        1%            19.6        23.4        18.9        20.0        18.8          57.7        58.7        (2)%  
 
    Cobalt by-products   t      175        246        192        182        179          553        506        9%            175        246        192        110        179          481        506        (5)%  

 

1

High quality refined nickel metal, including briquettes and powder.

 

2

Nickel sulphate crystals produced from nickel powder.

 

3

Nickel contained in matte and by-product streams.

 

10


BHP | Operational Review for the nine months ended 31 March 2024

 

Variance analysis relates to the relative performance of BHP and/or its operations during the nine months ended March 2024 compared with the nine months ended March 2023, unless otherwise noted. Production volumes, sales volumes and capital and exploration expenditure from subsidiaries are reported on a 100% basis; production and sales volumes from equity accounted investments and other operations are reported on a proportionate consolidation basis. Numbers presented may not add up precisely to the totals provided due to rounding.

The following abbreviations may have been used throughout this report: billion tonnes (Bt); cost and freight (CFR); cost, insurance and freight (CIF), carbon dioxide equivalent (CO2-e), dry metric tonne unit (dmtu); free on board (FOB); giga litres (GL); greenhouse gas (GHG); grams per cubic centimeter (g/cm3), grams per tonne (g/t); high-potential injury (HPI); kilograms per tonne (kg/t); kilometre (km); million ounces per annum (Mozpa); metres (m), million pounds (Mlb); million tonnes (Mt); million tonnes per annum (Mtpa); ounces (oz); OZ Minerals Limited (OZL); part per million (ppm), pounds (lb); thousand ounces (koz); thousand ounces per annum (kozpa); thousand tonnes (kt); thousand tonnes per annum (ktpa); thousand tonnes per day (ktpd); tonnes (t); total recordable injury frequency (TRIF); wet metric tonnes (wmt); and year to date (YTD).

In this release, the terms ‘BHP’, the ‘Group’, ‘BHP Group’, ‘we’, ‘us’, ‘our’ and ‘ourselves’ are used to refer to BHP Group Limited and, except where the context otherwise requires, our subsidiaries. Refer to note 30 ‘Subsidiaries’ of the Financial Statements in BHP’s 30 June 2023 Annual Report for a list of our significant subsidiaries. Those terms do not include non-operated assets. Notwithstanding that this release may include production, financial and other information from non-operated assets, non-operated assets are not included in the BHP Group and, as a result, statements regarding our operations, assets and values apply only to our operated assets unless stated otherwise. Our non-operated assets include Antamina and Samarco. BHP Group cautions against undue reliance on any forward-looking statement or guidance in this release. These forward-looking statements are based on information available as at the date of this release and are not guarantees or predictions of future performance and involve known and unknown risks, uncertainties and other factors, many of which are beyond our control and which may cause actual results to differ materially from those expressed in the statements contained in this release.

Further information on BHP can be found at bhp.com

Authorised for lodgement by:

Stefanie Wilkinson

Group Company Secretary

 

Media Relations    Investor Relations
Email: media.relations@bhp.com    Email: investor.relations@bhp.com
Australia and Asia    Australia and Asia
Gabrielle Notley    John-Paul Santamaria
Tel: +61 3 9609 3830 Mobile: +61 411 071 715    Mobile: +61 499 006 018
Europe, Middle East and Africa    Europe, Middle East and Africa
Neil Burrows    James Bell
Tel: +44 20 7802 7484 Mobile: +44 7786 661 683    Tel: +44 20 7802 7144 Mobile: +44 7961 636 432
Americas    Americas
Renata Fernandez    Monica Nettleton
Mobile: +56 9 8229 5357    Mobile: +1 416 518 6293
BHP Group Limited ABN 49 004 028 077   
LEI WZE1WSENV6JSZFK0JC28   
Registered in Australia   
Registered Office: Level 18, 171 Collins Street   
Melbourne Victoria 3000 Australia   
Tel +61 1300 55 4757 Fax +61 3 9609 3015   
BHP Group is headquartered in Australia   
Follow us on social media   

 

LOGO

 

11


SIGNATURES

Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused this report to be signed on its behalf by the undersigned, thereunto duly authorized.

 

      BHP Group Limited
Date: April 18, 2024     By:  

/s/ Stefanie Wilkinson

    Name:   Stefanie Wilkinson
    Title:   Group Company Secretary