v3.23.1
Commitments, Contingencies and Guarantees
3 Months Ended
Mar. 31, 2022
Commitments, Contingencies and Guarantees  
Commitments, Contingencies and Guarantees

9.         Commitments, Contingencies and Guarantees

In determining its accruals and disclosures with respect to loss contingencies, the Company will charge to income an estimated loss if information available prior to the issuance of the financial statements indicates that it is probable that a liability has been incurred at the date of the financial statements and the amount of the loss can be reasonably estimated. Legal expenses associated with the commitments and contingencies are expensed as incurred. If a loss contingency is not probable or reasonably estimable, disclosure of the loss contingency is made in the financial statements when it is at least reasonably possible that a material loss could be incurred.

Environmental Contingencies

The Company’s mining and exploration activities are subject to various laws, regulations and permits governing the protection of the environment. These laws, regulations and permits are continually changing and are generally becoming more restrictive. The Company has made, and expects to make in the future, expenditures to comply with such laws, regulations and permits, but cannot predict the full amount of such future expenditures.

Legal

On February 22, 2022, a purported Gatos stockholder filed a putative class action lawsuit in the United States District Court for the District of Colorado against the Company, certain of our former officers, and several directors. An amended complaint was filed on August 15, 2022. The amended complaint, allegedly brought on behalf of certain purchasers of Gatos common stock and certain traders of call and put options on Gatos common stock from December 9, 2020 through January 25, 2022, seeks, among other things, damages, costs, and expenses, and asserts claims under Sections 10(b) and 20(a) of the Securities Exchange Act of 1934 as well as Sections 11 and 15 of the Securities Act of 1933. The amended complaint alleges that certain individual defendants and Gatos, pursuant to the control and authority of the individual defendants, made false and misleading statements and/or omitted certain material information regarding the mineral resources and reserves at the Cerro Los Gatos mine. Gatos and all defendants filed a motion to dismiss this action on October 14, 2022. That motion was fully briefed as of December 23, 2022.

By Notice of Action issued February 9, 2022 and subsequent Statement of Claim dated March 11, 2022 Izabela Przybylska commenced a putative class action against Gatos Silver, Inc. (“Gatos”), certain of its former officers and directors, and others in the Ontario Superior Court of Justice on behalf of a purported class of all persons or entities, wherever they may reside or be domiciled, who acquired securities of Gatos in both the primary and secondary markets during the period from October 28, 2020 until January 25, 2022. The action asserts claims under Canadian securities legislation and at common law and seeks unspecified monetary damages and other relief in respect of allegations the defendants made false and misleading statements and omitted material information regarding the mineral resources and reserves of Gatos. The plaintiff filed motion materials for leave to proceed in respect of her statutory claims and for class certification on March 3, 2023. The court has tentatively set dates in late March of 2024 for the hearing of the plaintiff’s motions.

There can be no assurance that any of the foregoing matters individually or in aggregate will not result in outcomes that are materially adverse for us.

Dowa Debt Agreements

In July 2017, the LGJV operating entities consisting of Minera Plata Real S. de R.L. de C.V (“MPR”) and Operaciones San Jose del Plata S. de R.L. de C.V. (collectively, the “LGJV Entities”) entered into a loan agreement (the “Term Loan”) with Dowa whereby the LGJV Entities could borrow up to $210,000 for Los Gatos District (“LGD”) development, with a maturity date of December 29, 2027. Interest on the Term Loan accrued daily at LIBOR plus 2.35% per annum, with the interest added to the amount borrowed until commencement of production. During 2018, the LGJV paid Dowa a $4,200 closing fee. Commencing June 30, 2021, repayment of the Term Loan in 14 consecutive semi-annual equal payments of the aggregate principal and capitalized interest began. The Company was required to pay an arrangement fee on the borrowing, calculated as 2% per annum of 70% of the outstanding principal balance, payable in semi-annual installments, on that date which was two business days prior to June 30 and December 31 each fiscal year until maturity, commencing after the initial drawdown which occurred in July 2018. The Term Loan also required additional principal payments equal to 70% of excess cash flows (as defined).

On July 26, 2021, the Term Loan was repaid in full through capital contributions made to the LGJV by the Company and Dowa in pro-rata amounts equal to their ownership in the LGJV of 70% and 30%, respectively. In conjunction with the repayment, the Company paid a fee to Dowa of $10,000.

On January 23, 2018, the LGJV entered into a loan agreement with Dowa (the “Dowa MPR Loan”) whereby the LGJV could borrow up to $65,700 to continue LGD development. Interest on this loan accrued daily at LIBOR plus 1.5% per annum and was added to the amount borrowed. The amount borrowed plus accrued interest was due the earlier of June 30, 2019, or upon the Cerro Los Gatos mine’s substantial completion. If the Company’s 70% portion of the Dowa MPR Loan was not repaid in full on or before the due date, Dowa could elect to convert all or a portion of the principal amount into additional LGJV ownership at a favorable conversion rate.

In connection with entering into the WCF (as defined below), the Company contributed $18,200 to the LGJV in May 2019 to provide funding for partial repayment of principal and interest related to the Dowa MPR Loan. In late May 2019, the Dowa MPR Loan was fully extinguished with a cash payment of $18,200 and the conversion of the remaining $50,737 of principal and interest. The conversion of the remaining principal and interest increased Dowa’s ownership in the LGJV entities by 18.5% to 48.5%. On March 11, 2021, the Company repurchased the 18.5% interest from Dowa, for a total consideration of $71,550, increasing the Company’s ownership in the LGJV to 70.0%. These transactions resulted in a $47,400 higher basis than the underlying net assets of the LGJV Entities. This basis difference is being amortized as the LGJV Entities’ proven and probable reserves are processed.

On May 30, 2019, the LGJV entered into a working capital facility agreement (the “WCF”) with Dowa whereby the LGJV could borrow up to $60,000 to fund the working capital and sustaining capital requirements of the LGD. Interest on this loan accrued daily at LIBOR plus 3.0% per annum and all outstanding principal and interest was to mature on June 28, 2021. The Company was required to pay an arrangement fee on the borrowing, calculated as 15.0% per annum of 70.0% of the average daily principal amount outstanding under the WCF during such fiscal quarter. On March 11, 2021, the $60,000 outstanding under the WCF was extinguished using funds contributed to the LGJV. The Company’s pro-rata capital contribution to the LGJV was $42,000.

The Company guarantees the payment of all obligations, including accrued interest, under the LGJV equipment loan agreements. As of March 31, 2022, the LGJV had $4,059 outstanding under the LGJV equipment loan agreements, net of unamortized debt discount of $10, with maturity dates through August 2023.